Future IT Sourcing Programme (FITS) (MOJ) appears in 4 snapshots of the UK GMPP, from 2012 Sep to 2015 Sep.
Its cost is £1.7b at 2015 Sep, against £138m at 2012 Sep: +1132%.
Its planned finish is 30 Nov 2017, 35 months later than the 31 Dec 2014 first planned.
Its latest rating is Amber/Red (2015 Sep), down from Amber at 2012 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Future IT Sourcing Programme (FITS). Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/futureitsourcingprogrammefits, as at 31 Mar 2026. Licence: OGL v3.
How much does Future IT Sourcing Programme (FITS) cost? Its cost is £1.7b at 2015 Sep, against £138m at 2012 Sep: +1132%.
Is Future IT Sourcing Programme (FITS) late? Its planned finish is 30 Nov 2017, 35 months later than the 31 Dec 2014 first planned.
What is Future IT Sourcing Programme (FITS)'s latest rating? Its latest rating is Amber/Red (2015 Sep), down from Amber at 2012 Sep.