Further Electrification of Midland Main Line (MML3) (DFT) appears in 2 snapshots of the UK GMPP, from 2022 Mar to 2024 Mar.
Its cost is £1.5b at 2024 Mar, against £1.5b at 2022 Mar: no change.
Its planned finish is 31 Dec 2032, 24 months later than the 31 Dec 2030 first planned.
Its latest rating is Amber (2024 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Further Electrification of Midland Main Line (MML3). Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/furtherelectrificationofmidlandmainlinemml3, as at 31 Mar 2026. Licence: OGL v3.
How much does Further Electrification of Midland Main Line (MML3) cost? Its cost is £1.5b at 2024 Mar, against £1.5b at 2022 Mar: no change.
Is Further Electrification of Midland Main Line (MML3) late? Its planned finish is 31 Dec 2032, 24 months later than the 31 Dec 2030 first planned.
What is Further Electrification of Midland Main Line (MML3)'s latest rating? Its latest rating is Amber (2024 Mar).