Fraud, Error and Debt Programme (DWP) appears in 7 snapshots of the UK GMPP, from 2013 Sep to 2019 Sep.
Its cost is £1.2b at 2019 Sep, against £770m at 2013 Sep: +58%.
Its planned finish is 1 Dec 2020, 68 months later than the 31 Mar 2015 first planned.
Its latest rating is Amber/Green (2019 Sep), up from Amber/Red at 2013 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Fraud, Error and Debt Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/frauderroranddebtprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Fraud, Error and Debt Programme cost? Its cost is £1.2b at 2019 Sep, against £770m at 2013 Sep: +58%.
Is Fraud, Error and Debt Programme late? Its planned finish is 1 Dec 2020, 68 months later than the 31 Mar 2015 first planned.
What is Fraud, Error and Debt Programme's latest rating? Its latest rating is Amber/Green (2019 Sep), up from Amber/Red at 2013 Sep.