FE Capital Transformation (DFE) appears in 3 snapshots of the UK GMPP, from 2024 Mar to 2026 Mar.
Its planned finish is 30 Sep 2029, 42 months later than the 31 Mar 2026 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): FE Capital Transformation. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/fecapitaltransformation, as at 31 Mar 2026. Licence: OGL v3.
Is FE Capital Transformation late? Its planned finish is 30 Sep 2029, 42 months later than the 31 Mar 2026 first planned.
What is FE Capital Transformation's latest rating? Its latest rating is Amber (2026 Mar).