CSC Local Service Provider (LSP) Delivery Programme (CSV) appears in 2 snapshots of the UK GMPP, from 2016 Sep to 2017 Sep.
Its cost is £2.1b at 2017 Sep, against £2.1b at 2016 Sep: +0%.
Its planned finish is 31 Mar 2018, 3 months later than the 31 Dec 2017 first planned.
Its latest rating is Amber/Green (2017 Sep).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): CSC Local Service Provider (LSP) Delivery Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/csclocalserviceproviderlspdeliveryprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does CSC Local Service Provider (LSP) Delivery Programme cost? Its cost is £2.1b at 2017 Sep, against £2.1b at 2016 Sep: +0%.
Is CSC Local Service Provider (LSP) Delivery Programme late? Its planned finish is 31 Mar 2018, 3 months later than the 31 Dec 2017 first planned.
What is CSC Local Service Provider (LSP) Delivery Programme's latest rating? Its latest rating is Amber/Green (2017 Sep).