COLLECTIVE TRAINING TRANSFORMATION PROGRAMME (MOD) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its cost is £2.1b at 2026 Mar, against £974m at 2023 Mar: +114%.
Its planned finish is 10 Jun 2040, 2 months later than the 31 Mar 2040 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): COLLECTIVE TRAINING TRANSFORMATION PROGRAMME. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/collectivetrainingtransformationprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does COLLECTIVE TRAINING TRANSFORMATION PROGRAMME cost? Its cost is £2.1b at 2026 Mar, against £974m at 2023 Mar: +114%.
Is COLLECTIVE TRAINING TRANSFORMATION PROGRAMME late? Its planned finish is 10 Jun 2040, 2 months later than the 31 Mar 2040 first planned.
What is COLLECTIVE TRAINING TRANSFORMATION PROGRAMME's latest rating? Its latest rating is Amber (2026 Mar).