CLYDE INFRASTRUCTURE (MOD) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its cost is £3.3b at 2026 Mar, against £1.9b at 2023 Mar: +78%.
Its planned finish is 1 Apr 2032, unchanged from the 1 Apr 2032 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): CLYDE INFRASTRUCTURE. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/clydeinfrastructure, as at 31 Mar 2026. Licence: OGL v3.
How much does CLYDE INFRASTRUCTURE cost? Its cost is £3.3b at 2026 Mar, against £1.9b at 2023 Mar: +78%.
Is CLYDE INFRASTRUCTURE late? Its planned finish is 1 Apr 2032, unchanged from the 1 Apr 2032 first planned.
What is CLYDE INFRASTRUCTURE's latest rating? Its latest rating is Amber (2026 Mar).