Cerberus (HO) appears in 6 snapshots of the UK GMPP, from 2021 Mar to 2026 Mar.
Its cost is £285m at 2026 Mar, against £172m at 2021 Mar: +66%.
Its planned finish is 31 Mar 2030, 72 months later than the 1 Apr 2024 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Cerberus. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/cerberus, as at 31 Mar 2026. Licence: OGL v3.
How much does Cerberus cost? Its cost is £285m at 2026 Mar, against £172m at 2021 Mar: +66%.
Is Cerberus late? Its planned finish is 31 Mar 2030, 72 months later than the 1 Apr 2024 first planned.
What is Cerberus's latest rating? Its latest rating is Amber (2026 Mar).