Broadband Delivery Programme (DCMS) appears in 3 snapshots of the UK GMPP, from 2012 Sep to 2016 Sep.
Its cost is £2.2b at 2016 Sep, against £529m at 2012 Sep: +320%.
Its planned finish is 31 Dec 2020, 69 months later than the 31 Mar 2015 first planned.
Its latest rating is Amber/Green (2016 Sep), up from Amber/Red at 2012 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Broadband Delivery Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/broadbanddeliveryprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Broadband Delivery Programme cost? Its cost is £2.2b at 2016 Sep, against £529m at 2012 Sep: +320%.
Is Broadband Delivery Programme late? Its planned finish is 31 Dec 2020, 69 months later than the 31 Mar 2015 first planned.
What is Broadband Delivery Programme's latest rating? Its latest rating is Amber/Green (2016 Sep), up from Amber/Red at 2012 Sep.