BRIMSTONE 3 (MOD) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its planned finish is 31 Jan 2031, 21 months later than the 30 Apr 2029 first planned.
Its latest rating is Amber (2026 Mar), up from Red at 2023 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): BRIMSTONE 3. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/brimstone3, as at 31 Mar 2026. Licence: OGL v3.
Is BRIMSTONE 3 late? Its planned finish is 31 Jan 2031, 21 months later than the 30 Apr 2029 first planned.
What is BRIMSTONE 3's latest rating? Its latest rating is Amber (2026 Mar), up from Red at 2023 Mar.