Automatic Enrolment Programme (CSV) appears in 4 snapshots of the UK GMPP, from 2014 Sep to 2017 Sep.
Its planned finish is 30 Nov 2019, 12 months later than the 30 Nov 2018 first planned.
Its latest rating is Amber/Green (2017 Sep), up from Amber at 2014 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Automatic Enrolment Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/automaticenrolmentprogramme, as at 31 Mar 2026. Licence: OGL v3.
Is Automatic Enrolment Programme late? Its planned finish is 30 Nov 2019, 12 months later than the 30 Nov 2018 first planned.
What is Automatic Enrolment Programme's latest rating? Its latest rating is Amber/Green (2017 Sep), up from Amber at 2014 Sep.