A66 Northern Trans-Pennine (DFT) appears in 4 snapshots of the UK GMPP, from 2021 Mar to 2026 Mar.
Its planned finish is 1 Nov 2026, 41 months earlier than the 31 Mar 2030 first planned.
Its latest rating is Amber (2026 Mar), down from Green at 2021 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): A66 Northern Trans-Pennine. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/a66northerntranspennine, as at 31 Mar 2026. Licence: OGL v3.
Is A66 Northern Trans-Pennine late? Its planned finish is 1 Nov 2026, 41 months earlier than the 31 Mar 2030 first planned.
What is A66 Northern Trans-Pennine's latest rating? Its latest rating is Amber (2026 Mar), down from Green at 2021 Mar.