A417 AIR BALLOON (DFT) appears in 5 snapshots of the UK GMPP, from 2021 Mar to 2026 Mar.
Its planned finish is 31 Aug 2027, 26 months later than the 30 Jun 2025 first planned.
Its latest rating is Green (2026 Mar), up from Amber/Green at 2021 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): A417 AIR BALLOON. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/a417airballoon, as at 31 Mar 2026. Licence: OGL v3.
Is A417 AIR BALLOON late? Its planned finish is 31 Aug 2027, 26 months later than the 30 Jun 2025 first planned.
What is A417 AIR BALLOON's latest rating? Its latest rating is Green (2026 Mar), up from Amber/Green at 2021 Mar.