100000 Genomes Project (CSV) appears in 2 snapshots of the UK GMPP, from 2016 Sep to 2017 Sep.
Its cost is £393m at 2017 Sep, against £350m at 2016 Sep: +12%.
Its planned finish is 31 Dec 2018, 12 months later than the 31 Dec 2017 first planned.
Its latest rating is Amber (2017 Sep), up from Amber/Red at 2016 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): 100000 Genomes Project. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/100000genomesproject, as at 31 Mar 2026. Licence: OGL v3.
How much does 100000 Genomes Project cost? Its cost is £393m at 2017 Sep, against £350m at 2016 Sep: +12%.
Is 100000 Genomes Project late? Its planned finish is 31 Dec 2018, 12 months later than the 31 Dec 2017 first planned.
What is 100000 Genomes Project's latest rating? Its latest rating is Amber (2017 Sep), up from Amber/Red at 2016 Sep.