ieMR Program (FP3 and 4) (QH) appears in one Queensland DPD snapshot, 2026-09-02.
Its cost is $332m at 2026-09-02, against $86m at its baseline: +286%.
The source flags a delivery delay.
Its latest rating is Green (2026-09-02).
Cite: Queensland Government (per-agency contributions) (2026). Queensland Digital Projects Dashboard: ieMR Program (FP3 and 4). Tollgate Data, https://data.tollgatehq.com/projects/qld-dpd/qhiemrprogramfp3and4, as at 30 Aug 2026. Licence: CC BY 4.0.
How much does ieMR Program (FP3 and 4) cost? Its cost is $332m at 2026-09-02, against $86m at its baseline: +286%.
Is ieMR Program (FP3 and 4) late? The source flags a delivery delay.
What is ieMR Program (FP3 and 4)'s latest rating? Its latest rating is Green (2026-09-02).