Queensland Digital Projects Dashboard: 33% of 147 projects now cost more than their baseline figure, as at 30 Aug 2026.
Cite: Queensland Government (per-agency contributions) (2026). Queensland Digital Projects Dashboard. Tollgate Data, https://data.tollgatehq.com/datasets/qld-dpd, as at 30 Aug 2026. Licence: CC BY 4.0.
What share of Queensland DPD projects cost more than their baseline? 33% of 147 projects now cost more than their baseline figure. Queensland Digital Projects Dashboard: baseline and current cost taken from the same row, the project's latest snapshot; nominal, no CPI adjustment.
What share of Queensland DPD projects finish later than planned? The source reports 80% of 96 projects finishing late. Queensland Digital Projects Dashboard: the source's own delay flag, not a date comparison: a project counts as late when the flag is set.
How many Queensland DPD projects are rated Red? 2.7% of the 147 projects rated at 2 Sep 2026 were Red. Queensland Digital Projects Dashboard: status as the source published it at each snapshot.
Do bigger Queensland DPD projects overrun more often? Cost sits above baseline for 16% to 50% of projects across the four size bands. Queensland Digital Projects Dashboard: share of projects above baseline cost, by quartile of project size. Association, not cause.