Services Australia Improved Safety for Staff and Customers Phase 2 (Services Australia) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $362m at 2026, against $314m at 2025: +15%.
Its planned finish is 1 Jul 2026, unchanged from the 30 Jun 2026 first planned.
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Services Australia Improved Safety for Staff and Customers Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/servicesaustraliaimprovedsafetyforstaffandcustomersphase2, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Services Australia Improved Safety for Staff and Customers Phase 2 cost? Its cost is $362m at 2026, against $314m at 2025: +15%.
Is Services Australia Improved Safety for Staff and Customers Phase 2 late? Its planned finish is 1 Jul 2026, unchanged from the 30 Jun 2026 first planned.