DTA Major Digital Projects Report (Australia): 28% of 75 projects now cost more than their baseline figure, as at 27 May 2026.
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia). Tollgate Data, https://data.tollgatehq.com/datasets/mdpr, as at 27 May 2026. Licence: CC BY 3.0 AU.
What share of DTA MDPR projects cost more than their baseline? 28% of 75 projects now cost more than their baseline figure. DTA Major Digital Projects Report (Australia): the cost at the project's first snapshot against the cost at its latest; nominal, no CPI adjustment.
What share of DTA MDPR projects finish later than planned? The source reports 39% of 76 projects finishing late. DTA Major Digital Projects Report (Australia): calendar months between the completion date at the project's first snapshot and the date at its latest.
How many DTA MDPR projects are rated Medium or lower? 44% of the 59 projects rated in 2026 were Medium or lower on delivery confidence. DTA Major Digital Projects Report (Australia): status as the source published it at each snapshot.
Do bigger DTA MDPR projects overrun more often? Cost sits above baseline for 5.3% to 42% of projects across the four size bands. DTA Major Digital Projects Report (Australia): share of projects above baseline cost, by quartile of project size. Association, not cause.
How many DTA MDPR projects enter and leave each snapshot? 39% of the 127 projects seen before 2026 are absent from it. DTA Major Digital Projects Report (Australia): each bar holds the projects continuing from the previous snapshot and those entering at this one, so it is that snapshot's own population.