Safely Connecting Australians with Support (Services Australia) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $50m at 2026, against $30m at 2025: +66%.
Its planned finish is 1 Jun 2026, 11 months later than the 30 Jun 2025 first planned.
Its latest rating is Medium-High (2026).
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Safely Connecting Australians with Support. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/safelyconnectingaustralianswithsupport, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Safely Connecting Australians with Support cost? Its cost is $50m at 2026, against $30m at 2025: +66%.
Is Safely Connecting Australians with Support late? Its planned finish is 1 Jun 2026, 11 months later than the 30 Jun 2025 first planned.
What is Safely Connecting Australians with Support's latest rating? Its latest rating is Medium-High (2026).