Reporting and Program Management (RPM) System (Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $31m at 2026, against $19m at 2025: +66%.
Its planned finish is 1 Jun 2026, 1 months earlier than the 30 Jun 2026 first planned.
Its latest rating is High (2026).
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Reporting and Program Management (RPM) System. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/reportingandprogrammanagementrpmsystem, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Reporting and Program Management (RPM) System cost? Its cost is $31m at 2026, against $19m at 2025: +66%.
Is Reporting and Program Management (RPM) System late? Its planned finish is 1 Jun 2026, 1 months earlier than the 30 Jun 2026 first planned.
What is Reporting and Program Management (RPM) System's latest rating? Its latest rating is High (2026).