RegistryConnect Program (Australian Securities and Investments Commission) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $362m at 2026, against $155m at 2025: +134%.
Its planned finish is 1 Jun 2030, 5 months later than the 31 Dec 2029 first planned.
Its latest rating is Medium-High (2026).
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): RegistryConnect Program. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/registryconnectprogram, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does RegistryConnect Program cost? Its cost is $362m at 2026, against $155m at 2025: +134%.
Is RegistryConnect Program late? Its planned finish is 1 Jun 2030, 5 months later than the 31 Dec 2029 first planned.
What is RegistryConnect Program's latest rating? Its latest rating is Medium-High (2026).