Investigation Management Solution (IMS) Program (Australian Federal Police) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $54m at 2026, against $45m at 2025: +21%.
Its planned finish is 1 Jun 2025, 1 months earlier than the 30 Jun 2025 first planned.
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Investigation Management Solution (IMS) Program. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/investigationmanagementsolutionimsprogram, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Investigation Management Solution (IMS) Program cost? Its cost is $54m at 2026, against $45m at 2025: +21%.
Is Investigation Management Solution (IMS) Program late? Its planned finish is 1 Jun 2025, 1 months earlier than the 30 Jun 2025 first planned.