Digital First (DF) Program (National Archives of Australia) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $25m at 2026, against $36m at 2025: -31%.
Its planned finish is 1 Jun 2026, 13 months earlier than the 30 Jun 2027 first planned.
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Digital First (DF) Program. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/digitalfirstdfprogram, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Digital First (DF) Program cost? Its cost is $25m at 2026, against $36m at 2025: -31%.
Is Digital First (DF) Program late? Its planned finish is 1 Jun 2026, 13 months earlier than the 30 Jun 2027 first planned.