Data and Regulatory Transformation (DART) Program (NDIS Quality and Safeguards Commission) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $160m at 2026, against $160m at 2025: no change.
Its planned finish is 1 Jun 2028, 1 months earlier than the 30 Jun 2028 first planned.
Its latest rating is Medium (2026).
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Data and Regulatory Transformation (DART) Program. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/dataandregulatorytransformationdartprogram, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Data and Regulatory Transformation (DART) Program cost? Its cost is $160m at 2026, against $160m at 2025: no change.
Is Data and Regulatory Transformation (DART) Program late? Its planned finish is 1 Jun 2028, 1 months earlier than the 30 Jun 2028 first planned.
What is Data and Regulatory Transformation (DART) Program's latest rating? Its latest rating is Medium (2026).