Cyber Security Upgrades to Reduce Exposure (CURE) Program - Phase 2 (Department of the Prime Minister and Cabinet) appears in 2 snapshots of the DTA MDPR, from 2025 to 2026.
Its cost is $23m at 2026, against $23m at 2025: no change.
Its planned finish is 1 Jun 2025, 1 months earlier than the 30 Jun 2025 first planned.
Its latest rating is Medium-High (2026).
Cite: Digital Transformation Agency (2026). DTA Major Digital Projects Report (Australia): Cyber Security Upgrades to Reduce Exposure (CURE) Program - Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/mdpr/cybersecurityupgradestoreduceexposurecureprogramphase2, as at 27 May 2026. Licence: CC BY 3.0 AU.
How much does Cyber Security Upgrades to Reduce Exposure (CURE) Program - Phase 2 cost? Its cost is $23m at 2026, against $23m at 2025: no change.
Is Cyber Security Upgrades to Reduce Exposure (CURE) Program - Phase 2 late? Its planned finish is 1 Jun 2025, 1 months earlier than the 30 Jun 2025 first planned.
What is Cyber Security Upgrades to Reduce Exposure (CURE) Program - Phase 2's latest rating? Its latest rating is Medium-High (2026).