SmartRider (Public Transport Authority) appears in one WA OAG ICT audit snapshot, 2025.
Its cost is $68m at 2025, against $35m at its baseline: +95%.
Its planned finish is 1 Jun 2026, 78 months later than the 1 Dec 2019 first planned.
Cite: Office of the Auditor General WA (2025). WA OAG Status of Public Sector ICT Projects: SmartRider. Tollgate Data, https://data.tollgatehq.com/projects/wa-oag/smartrider, as at 16 Jun 2025. Licence: All rights reserved.
How much does SmartRider cost? Its cost is $68m at 2025, against $35m at its baseline: +95%.
Is SmartRider late? Its planned finish is 1 Jun 2026, 78 months later than the 1 Dec 2019 first planned.